Rick Hendricks, Director, Property Development Division, Public Buildings Service, National Capital Region, General Services Administration
Testimony to the House of Representatives Committee on Government Reform and Oversight Subcommittee on the District of Columbia
July 15, 1998

Home

Bibliography

Calendar

Columns
Dorothy Brizill
Bonnie Cain
Jim Dougherty
Gary Imhoff
Phil Mendelson
Mark David Richards
Sandra Seegars

DCPSWatch

DCWatch Archives
Council Period 12
Council Period 13
Council Period 14

Election 1998
Election 2000
Election 2002

Elections
Election 2004
Election 2006

Government and People
ANC's
Anacostia Waterfront Corporation
Auditor
Boards and Com
BusRegRefCom
Campaign Finance
Chief Financial Officer
Chief Management Officer
City Council
Congress
Control Board
Corporation Counsel
Courts
DC2000
DC Agenda
Elections and Ethics
Fire Department
FOI Officers
Inspector General
Health
Housing and Community Dev.
Human Services
Legislation
Mayor's Office
Mental Health
Motor Vehicles
Neighborhood Action
National Capital Revitalization Corp.
Planning and Econ. Dev.
Planning, Office of
Police Department
Property Management
Public Advocate
Public Libraries
Public Schools
Public Service Commission
Public Works
Regional Mobility Panel
Sports and Entertainment Com.
Taxi Commission
Telephone Directory
University of DC
Water and Sewer Administration
Youth Rehabilitation Services
Zoning Commission

Issues in DC Politics

Budget issues
DC Flag
DC General, PBC
Gun issues
Health issues
Housing initiatives
Mayor’s mansion
Public Benefit Corporation
Regional Mobility
Reservation 13
Tax Rev Comm
Term limits repeal
Voting rights, statehood
Williams’s Fundraising Scandals

Links

Organizations
Appleseed Center
Cardozo Shaw Neigh.Assoc.
Committee of 100
Fed of Citizens Assocs
League of Women Voters
Parents United
Shaw Coalition

Photos

Search

What Is DCWatch?

themail archives

Good morning Mr. Chairman and members of the subcommittee, my name is Rick Hendricks and I am the Director of the Property Development Division in the National Capital Region for General Services Administration (GSA). Thank you for the opportunity to appear before you today to describe GSA's involvement in the DC Convention Center construction contract.

We at GSA have been working with the Washington Convention Center Authority (WCCA), at their request, for over a year. In August 1997, WCCA sought our opinion and recommendations regarding the design-build solicitation that was on the market at that time (offers were due September 8, 1997). WCCA believed that they were only going to receive one offer. GSA recommended that they cancel the procurement and change the solicitation strategy to attract more competition. WCCA did receive only one offer and it exceeded the budget. GSA reviewed the proposal and determined that it was approximately $100 million too high and could not be value-engineered within the budgeted cost. GSA again recommended the procurement be cancelled and reissued using the Construction Management at Risk (CM at risk ) method to get the project cost under control and still remain on schedule. CM at risk means that the owner selects a contractor to perform construction management services and construction work in accordance with the plans and specification for a fixed fee and the contractor guarantees the maximum construction price.

The issues that must be managed on such a project include: price competition, design and construction control, risks to the involved parties, relationships and the project cost. GSA recommended that the WCCA pursue an “at risk” construction manager as constructor (CMc) contract. Experience has shown that this method of contracting helps to minimize adversarial relationships between the parties, thus reducing claims and change orders. It was felt that this type of contract would eliminate barriers to competition and encourage more firms to submit proposals. Such a competitive procurement process should produce prices more in line with the Government’s project estimate. The resultant contract would produce a controllable and predictable Guaranteed Maximum Price (GMP) and schedule for the construction. WCCA would retain control over the design while the CMc would assume control over the construction to manage risks, means and methods to bring the project in on schedule and within the GMP.

WCCA rejected the lone bid because it failed to meet technical requirements in its proposal and significantly exceeded the cost estimated. Their subsequent solicitation for a guaranteed maximum price CMc contract produced four competitive proposals.

For this testimony, I have reviewed Clark-Smoot’s guaranteed maximum price proposal. We feel that WCCA chose the appropriate contracting vehicle for their new Convention Center. One of the things the CMc contract does is to define the risks of both parties. In this manner, the contractor is better able to quantify the costs associated with those risks. WCCA has incorporated the normal GMP provisions into the contract to place the risk of meeting the project schedule and costs on the constructor. WCCA has obtained unit prices for hazardous material in what I consider to be an effort to minimize unknown risks to the contractor. While this action will place risk on the WCCA, the cost impact will still be less than if the contractor included the price for that unknown risk within the GMP. WCCA developed creative arrangements to reduce up-front costs by proposing a long term service contract with a Thermal Energy Services Provider (TESP) to build a plant and then recover the capital outlay through higher operating charges during the life of the contract. They have incorporated affirmative action goals in the contract and are making every reasonable effort to afford District of Columbia residents, minorities, and women (residents of Shaw neighborhood are included in DC residents), as well as Local, Small, or Disadvantaged Business Enterprises, with opportunities to participate in the project. Provisions have been made that in the event an acceptable Guaranteed Maximum Price and Project Schedule are not developed, the contract will be terminated and WCAA will only be obligated to pay the construction manager the preconstruction fee.

In conclusion, GSA finds the proposed contract for the Washington Convention Center to be appropriate. While construction contracting by its nature is an inherently risky business, this contract appears to have a high probability of satisfactorily achieving its stated purpose of constructing the Washington Convention Center within budget and on schedule and establishes a reasonable allocation of risks.

Again, Thank you for inviting me to appear before the subcommittee today. I will be happy to answer any questions about our involvement in the DC Convention Center construction contract.